What to check, how often and who should do it, from fixed wiring and emergency lighting to air conditioning and plant.
Blog
What mechanical and electrical checks does your building need?
A commercial building needs four mechanical and electrical checks on fixed dates: an inspection of the fixed wiring, monthly and annual emergency lighting tests, an energy inspection for larger air conditioning systems, and F gas leak checks on systems holding enough refrigerant. Everything else, from air handling units to pumps and distribution boards, is serviced to the manufacturer's intervals and the risk it carries.
This post sets out each check, how often it falls due and who should carry it out, so you can build one schedule for your building. It is general guidance. The exact duties depend on how the building is used and who is responsible for it, so confirm the detail with a competent person for your site.
What the law asks of you
Two sets of regulations sit behind most mechanical and electrical maintenance. The Electricity at Work Regulations 1989 say electrical systems must be maintained "so as to prevent, so far as is reasonably practicable" danger. The Workplace (Health, Safety and Welfare) Regulations 1992 say a workplace's equipment and systems, including mechanical ventilation, must be kept in efficient working order and good repair.
Neither gives you a timetable. They set a duty, and your records are how you show you met it. That is why the fixed dates below matter, and why the work in between needs writing down too.
Fixed wiring inspection, every three to five years
An Electrical Installation Condition Report, or EICR, is a full inspection and test of the building's fixed wiring: the distribution boards (the panels of circuit breakers that feed each area), the circuits, sockets, switches and fixed equipment. It records any defects and how urgent they are.
The IET's guidance on inspection and testing gives these maximum intervals:
Every five years for offices, shops, schools, hospitals, restaurants, hotels and pubs
Every three years for industrial units, leisure complexes and theatres
On a change of occupancy for commercial premises, whenever that falls
These are maximums. The inspector can set a shorter interval if the installation's condition calls for it, and the next due date is written on the report.
Emergency lighting, every month and every year
Emergency lighting has to come on when the mains fails, so it is tested in two ways. Every month, a short functional test uses the test key switch to simulate a power cut and confirm each fitting lights. Once a year, a full-duration test runs the system on its batteries for its rated time, usually three hours, as set out in BS 5266-1.
Log every test with the location of each fitting, any faults found and when they were fixed. Because the annual test drains the batteries, plan it for a time when the building can manage without full emergency cover for the next day. Our fire service covers emergency lighting alongside fire detection.
Air conditioning, every year and every five years
Air conditioning brings two separate duties, one about energy and one about refrigerant.
Energy inspection every five years. A system, or several units under the same control in one building, with a combined rated output over 12kW needs an inspection at least every five years under the Energy Performance of Buildings Regulations. It is often called a TM44 inspection and must be carried out by an accredited energy assessor. The person who controls how the system runs arranges it, usually the owner or a contractor named in the contract.
F gas leak checks at least once a year. Systems holding refrigerant equal to 5 tonnes of CO2 or more must be checked for leaks at least every 12 months, every six months from 50 tonnes, and more often again above that. Fitting automatic leak detection doubles the interval. The tonnage is on the unit's label or service records.
Plant without a fixed legal date
Air handling units, extract fans, pumps and booster sets (pumps that raise water pressure to upper floors), electric motors and variable speed drives have no set inspection interval in law. They are covered by the general duty to keep them working and in good repair, so the manufacturer's servicing schedule is the usual starting point.
Then adjust for risk. A booster set serving a care home or a fan keeping a server room cool needs closer attention than one serving a storeroom. Typical servicing covers filters, belts, bearings, vibration, control settings and alarms. Our planned preventative maintenance checklist goes through these system by system.
Keeping every check on one schedule
The checks above fall on different cycles, from monthly to five-yearly, which is how dates get missed. Keep them in one place:
List every asset in an asset register, with its location and an ID.
Add each fixed date and each manufacturer interval against the asset.
Record every visit with the result, any defects and when they were closed.
Keep reports and certificates with the asset they relate to.
Auditors and insurers will usually ask for this trail. Our guide to what auditors look for in maintenance records covers how to set it out.
A commercial building needs four mechanical and electrical checks on fixed dates: an inspection of the fixed wiring, monthly and annual emergency lighting tests, an energy inspection for larger air conditioning systems, and F gas leak checks on systems holding enough refrigerant. Everything else, from air handling units to pumps and distribution boards, is serviced to the manufacturer's intervals and the risk it carries.
This post sets out each check, how often it falls due and who should carry it out, so you can build one schedule for your building. It is general guidance. The exact duties depend on how the building is used and who is responsible for it, so confirm the detail with a competent person for your site.
What the law asks of you
Two sets of regulations sit behind most mechanical and electrical maintenance. The Electricity at Work Regulations 1989 say electrical systems must be maintained "so as to prevent, so far as is reasonably practicable" danger. The Workplace (Health, Safety and Welfare) Regulations 1992 say a workplace's equipment and systems, including mechanical ventilation, must be kept in efficient working order and good repair.
Neither gives you a timetable. They set a duty, and your records are how you show you met it. That is why the fixed dates below matter, and why the work in between needs writing down too.
Fixed wiring inspection, every three to five years
An Electrical Installation Condition Report, or EICR, is a full inspection and test of the building's fixed wiring: the distribution boards (the panels of circuit breakers that feed each area), the circuits, sockets, switches and fixed equipment. It records any defects and how urgent they are.
The IET's guidance on inspection and testing gives these maximum intervals:
Every five years for offices, shops, schools, hospitals, restaurants, hotels and pubs
Every three years for industrial units, leisure complexes and theatres
On a change of occupancy for commercial premises, whenever that falls
These are maximums. The inspector can set a shorter interval if the installation's condition calls for it, and the next due date is written on the report.
Emergency lighting, every month and every year
Emergency lighting has to come on when the mains fails, so it is tested in two ways. Every month, a short functional test uses the test key switch to simulate a power cut and confirm each fitting lights. Once a year, a full-duration test runs the system on its batteries for its rated time, usually three hours, as set out in BS 5266-1.
Log every test with the location of each fitting, any faults found and when they were fixed. Because the annual test drains the batteries, plan it for a time when the building can manage without full emergency cover for the next day. Our fire service covers emergency lighting alongside fire detection.
Air conditioning, every year and every five years
Air conditioning brings two separate duties, one about energy and one about refrigerant.
Energy inspection every five years. A system, or several units under the same control in one building, with a combined rated output over 12kW needs an inspection at least every five years under the Energy Performance of Buildings Regulations. It is often called a TM44 inspection and must be carried out by an accredited energy assessor. The person who controls how the system runs arranges it, usually the owner or a contractor named in the contract.
F gas leak checks at least once a year. Systems holding refrigerant equal to 5 tonnes of CO2 or more must be checked for leaks at least every 12 months, every six months from 50 tonnes, and more often again above that. Fitting automatic leak detection doubles the interval. The tonnage is on the unit's label or service records.
Plant without a fixed legal date
Air handling units, extract fans, pumps and booster sets (pumps that raise water pressure to upper floors), electric motors and variable speed drives have no set inspection interval in law. They are covered by the general duty to keep them working and in good repair, so the manufacturer's servicing schedule is the usual starting point.
Then adjust for risk. A booster set serving a care home or a fan keeping a server room cool needs closer attention than one serving a storeroom. Typical servicing covers filters, belts, bearings, vibration, control settings and alarms. Our planned preventative maintenance checklist goes through these system by system.
Keeping every check on one schedule
The checks above fall on different cycles, from monthly to five-yearly, which is how dates get missed. Keep them in one place:
List every asset in an asset register, with its location and an ID.
Add each fixed date and each manufacturer interval against the asset.
Record every visit with the result, any defects and when they were closed.
Keep reports and certificates with the asset they relate to.
Auditors and insurers will usually ask for this trail. Our guide to what auditors look for in maintenance records covers how to set it out.
How we look after mechanical and electrical systems across your sites
FixBot is based in Bedford and looks after sites across the surrounding towns and in London, Birmingham, Manchester and Liverpool. Through our planned maintenance service we bring the dates for a building's mechanical and electrical systems into one programme, so checks are booked before they fall due rather than after. When something fails between visits, engineers attend with stocked vans and diagnostic kit, and each job is logged with photos and compliance notes for your records.
If you look after a commercial building and aren't sure when its mechanical and electrical checks are next due, FixBot can survey the site and set out a schedule. Find out more about our mechanical and electrical service and book a survey.